DN 73 Pitesti - Campulung - Brasov km 13+800-42+850; km 54+050-128+250
POIM · 2014-2020 · CNAIR · raportare la 31 august 2025
Argeş, Brașov · MySMIS 116018
Beneficiar: CNAIR.
The main objectives of this project are: Rehabilitation/ modernization of 103,25 kilometres of national roads, rehabilitation of 17 bridges, construction of seven new bridges (total bridges 24 pieces) and arrangement of 33 intersections. - reducing travel time between Piteşti and Braşov 9,1 minutes, from 116,9 min to 107,8 min; - reduction in operating costs of vehicles with 13%; - increase traffic safety: estimated 10% reduction in the number of accidents due to road modernization and implementation of measures to enhance safety.
- Început
- 19 mai 2014
- Finalizare planificată
- 31 decembrie 2023
- Stadiu publicat
- Proiect nefinalizat
- Valoare eligibilă
- 326.721.592 lei
- Valoare totală
- 414.045.059 lei
- Plăți publicate din fonduri UE
- 40.936.776 lei
- Plăți publicate din contribuția națională
- 11.571.869 lei
Stadiul, valorile și plățile sunt cele publicate în ediția programului. O valoare negativă a plăților poate reprezenta o corecție în fișierul publicat.